13.Weekly report _ from NND

 

WEEKLY REPORT (No.13)

 

 

Project: 14F Building

 

Date: 27th Feb 2020

1 - Follow up problem and obstacle before last week

1.      Steel door will deliver on 28th Feb 2020.

2.      Plywood door will deliver on 8th March 2020.

3.      KJKs deliver is waiting the payment 30%.

4.      Ceiling 15F,16F is waiting approval from Nordic. It is obstacle on site.

5.      Mirror, we will install after marble of lavatory finished.

6.      Mosquito net will install after louver installation on the back site.

7.      For the edge of roof, we are waiting the fabrication from Fuxin, ASMA just approved the shop drawing the additional price.

 

2 - Last week work progress

1.      For slab basement, we already casted concrete.

2.      For basement pit, we already casted concrete

3.      For retaining wall in front, we already casted concrete.

4.      For plastering brick wall external, we already complete 90%, it remained only section of hoist.

5.      For painting, we already apply second coat from 2F to 15F.

6.      We already made brick wall demolition 12F, 13F, 15F.

7.      We completed louver for back site 50%.

8.      We made ceiling installation for the missing part.

9.      We already installed handrail for balcony from 2nd to 15F.

3 - Next week work schedule

1.      We will cast concrete for slab of fresh water tanks on 29th Feb 2020.

2.      We will cast concrete for slab of ramp on 29th Feb 2020.

3.      We will cast concrete for the remaining slab ground on 5th March 2020.

4.      We will cast concrete for retaining wall for the left and back site on 7th March 2020.

5.      We will complete louver on the back site on 19th March 2020.

6.      We will finish the edge of roof revised the size by Asma on 11th March 2020.

7.      We will start brick wall installation on basement on 29th Feb 2020.

8.      We will install the small handrail for glass door AW-03 on 29th Feb 2020.

9.      We will install marble for lavatory on 1st March 2020.

10.   We will start finish second coat for balcony on 29th March 2020.

11.   We will start exterior painting on 2nd March 2020.

12.   We are installing access panel for ceiling and make rectification for the missing part.

13.   We are installing ceiling 17F.

14.   We will finish handrail painting on 7th March 2020.

 

4 - Problem and obstacle of the week and others

1.      We need the head office pay the money for supplier KJKS for delivery material on site to make installation.

2.      We would like head office follow up Fuxin to make edge fabrication

3.      We would like head office help to follow up Nordic to approved ceiling 15F,16F.

5 - Resolution, proposal & recommendation

 

To progress the work effectively, we would like the material on site as soon as possible.

 

Reported by Checked by

Site Engineer Project Manager

 

KEO Rany IN Bunlen