   WEEKLY
  REPORT (No.13)  | 
 |
| 
   Project:  14F Building    | 
  
   Date: 27th   Feb 2020  | 
 
                                                                        
                    
| 
   1
  - Follow up problem and obstacle before last week 1.     
  Steel door will
  deliver on 28th Feb 2020. 2.     
  Plywood door will
  deliver on 8th March 2020. 3.     
  KJKs deliver is
  waiting the payment 30%.  4.     
  Ceiling 15F,16F is
  waiting approval from Nordic. It is obstacle on site.  5.     
  Mirror, we will
  install after marble of lavatory finished. 6.     
  Mosquito net will
  install after louver installation on the back site. 7.     
  For the edge of
  roof, we are waiting the fabrication from Fuxin, ASMA just approved the shop
  drawing the additional price.   | 
 
| 
   2
  - Last week work progress 1.     
  For slab basement,
  we already casted concrete. 2.     
  For basement pit,
  we already casted concrete 3.     
  For retaining wall
  in front, we already casted concrete. 4.     
  For plastering
  brick wall external, we already complete 90%, it remained only section of
  hoist. 5.     
  For painting, we
  already apply second coat from 2F to 15F. 6.     
  We already made
  brick wall demolition 12F, 13F, 15F. 7.     
  We completed louver
  for back site 50%.  8.     
  We made ceiling
  installation for the missing part. 9.     
  We already
  installed handrail for balcony from 2nd to 15F.  | 
 
| 
   3
  - Next week work schedule 1.     
  We will cast
  concrete for slab of fresh water tanks on 29th Feb 2020. 2.     
  We will cast
  concrete for slab of ramp on 29th Feb 2020. 3.     
  We will cast
  concrete for the remaining slab ground on 5th March 2020. 4.     
  We will cast
  concrete for retaining wall for the left and back site on 7th
  March 2020. 5.     
  We will complete
  louver on the back site on 19th March 2020. 6.     
  We will finish the
  edge of roof revised the size by Asma on 11th March 2020. 7.     
  We will start brick
  wall installation on basement on 29th Feb 2020. 8.     
  We will install the
  small handrail for glass door AW-03 on 29th Feb 2020. 9.     
  We will install
  marble for lavatory on 1st March 2020. 10.  
  We will start
  finish second coat for balcony on 29th March 2020. 11.  
  We will start
  exterior painting on 2nd March 2020.  12.  
  We are installing
  access panel for ceiling and make rectification for the missing part. 13.  
  We are installing
  ceiling 17F. 14.  
  We will finish
  handrail painting on 7th March 2020.  | 
 
| 
   4
  - Problem and obstacle of the week and others 1.      We need the head office pay the money for supplier KJKS
  for delivery material on site to make installation. 2.      We would like head office follow up Fuxin to make edge
  fabrication 3.      We would like head office help to follow up Nordic to
  approved ceiling 15F,16F.  | 
 
| 
   5 - Resolution, proposal & recommendation To
  progress the work effectively, we would like the material on site as soon as
  possible.    | 
 
Reported by                                                                                                   Checked by
                                            Site Engineer                                                                                               Project Manager
                                             KEO
Rany               IN Bunlen