0. LIST OF REMAIN WORKING AT SITE 17FLOORS

LIST OF REMAIN WORKING AT SITE 17FLOORS(KPS)

Project: Apartment &Hotel 17floors (KPS) Date: 02/03/2020

Location: Sihanouk Ville Inform to: Constructor

N0.

Description

Detail of Working

Reference actual at site

I

Retaining Wall

 

1.1. Retaining Wall.pdf

1.2. Membrane.pdf

1

Cutting joint of each wall

There have many joint need to cut and fill if by sika swell

2

Membrane

Remain Membrane along the road and under U-Drain B

3

Wall Cleaning and repairing crack

Chip the concrete around the across steel, bend steel and fill by mortar with Sika latex

II

U-Drain

 

 

1

Remove formwork for U-Drain A, D

The formwork inside of U-Drain doesn t remove yet

2. U-Drain.pdf

2

Cleaning and repairing

Cleaning and repairing actual at site

3

Install and Casting concrete for U-Drain C and E

U-Drain C and E don t cast concrete yet. Need to install the formwork and casting

III.

Stair

 

 

1

Stair Type 3

Not yet start

3.1. Stair type 1.pdf

3.2. Stair Type 2.pdf

3.3. Stair Type 3.pdf

2

Cleaning on stair Type 1, 2 and curve stair

 

IV

Cleaning and repairing on floor

 

 

1

Ground floor

The concrete need to remove out and cleaning, cut the across steel

4.1. Ground to 2nd floor.pdf

4.2. 3rd to 16th floor.pdf

4.3. 17th floor and Swimming pool.pdf

4.4. Roof.pdf

2

1st to 3rd floor

Chip concrete some part of depress slab, repair some of kerbs, cut the across steel and check and repair the boundary slab, Groove line of ramp

3

4th to 16th floor

Chip concrete some part of depress slab, repair some of kerbs, cut the across steel and check and repair the boundary slab

4

17th floor and roof floor

Remove the formwork of U-drain of swimming pool, Chip concrete some part of depress slab, repair some of kerbs, cut the across steel of column and check and repair the boundary slab

V

New lift

 

 

1

Column and steel I installation

 

 

VI

Shear wall

 

 

1

Cleaning, cut across steel

 

 

2

Check and repairing position

 

VII

Slab cracked repairing

 

 

1

The 1st and 2nd floor

Repairing

 

VIII

Septic and Balancing tank

(Waiting on Wednesday, if the working does not start yet, schedule change)

 

 

Note: 1. One attachment schedule of working (file Excel attachment) and attachments reference in files pdf.

2. The limit of End schedule is the last date of finish all workings at site. In case, the workings at site still not completed following approved schedule, the constructor need to pay all things on construction (pay for penalties, management, means of construction etc.)

3. The owner (khmer) approved to pay only half month on management of construction and means of construction.

 

Prepared by: Checked and Approved by:

Y SOVANN LENG KHUN DADINO