LIST OF REMAIN WORKING AT SITE 17FLOORS(KPS)
Project: Apartment
&Hotel 17floors (KPS)
Date:
02/03/2020
Location: Sihanouk Ville
Inform to: Constructor
|
N0. |
Description |
Detail
of Working |
Reference
actual at site |
|
I |
Retaining Wall |
|
|
|
1 |
Cutting
joint of each wall |
There
have many joint need to cut and fill if by sika swell |
|
|
2 |
Membrane |
Remain
Membrane along the road and under U-Drain B |
|
|
3 |
Wall
Cleaning and repairing crack |
Chip
the concrete around the across steel,
bend steel and fill by mortar with Sika latex
|
|
|
II |
U-Drain |
|
|
|
1 |
Remove
formwork for U-Drain A, D |
The
formwork inside of U-Drain doesn t remove yet |
|
|
2 |
Cleaning
and repairing |
Cleaning
and repairing actual at site |
|
|
3 |
Install
and Casting concrete for U-Drain C and E |
U-Drain
C and E don t cast concrete yet. Need to install the formwork and casting |
|
|
III. |
Stair
|
|
|
|
1 |
Stair
Type 3 |
Not
yet start |
|
|
2 |
Cleaning
on stair Type 1, 2 and curve stair |
|
|
|
IV |
Cleaning
and repairing on floor |
|
|
|
1 |
Ground
floor |
The
concrete need to remove out and cleaning, cut the across steel |
|
|
2 |
1st
to 3rd floor |
Chip
concrete some part of depress slab, repair some of kerbs,
cut the across steel and check and repair the boundary slab, Groove line of
ramp |
|
|
3 |
4th
to 16th floor |
Chip
concrete some part of depress slab, repair some of kerbs,
cut the across steel and check and repair the boundary slab |
|
|
4 |
17th
floor and roof floor |
Remove
the formwork of U-drain of swimming pool, Chip concrete some part of depress
slab, repair some of kerbs, cut the across steel of
column and check and repair the
boundary slab |
|
|
V |
New lift |
|
|
|
1 |
Column and steel I installation |
|
|
|
VI |
Shear wall |
|
|
|
1 |
Cleaning,
cut across steel |
|
|
|
2 |
Check
and repairing position |
|
|
|
VII |
Slab cracked repairing |
|
|
|
1 |
The 1st
and 2nd floor |
Repairing |
|
|
VIII |
Septic
and Balancing tank |
(Waiting on Wednesday, if the working does not start
yet, schedule change) |
|
Note: 1. One attachment schedule of working (file
Excel attachment) and attachments reference in files pdf.
2. The limit of End schedule is the
last date of finish all workings at site. In case, the workings at site still
not completed following approved schedule, the constructor need to pay all
things on construction (pay for
penalties, management, means of construction etc.)
3. The owner (khmer) approved to pay only half month on management of
construction and means of construction.
Prepared
by: Checked
and Approved by:
Y
SOVANN LENG
KHUN DADINO