How to Assign Resources in Microsoft Project

Words: ...
↓ Down

How to Assign Resources in Microsoft Project

Assigning resources correctly is one of the most important steps in Microsoft Project. It allows you to:

  • Know who is responsible for each task

  • Calculate workload automatically

  • Identify overallocated workers

  • Forecast labor requirements

  • Perform Resource Leveling correctly


Step 1: Create Your Resource List

Go to Resource Sheet

  1. Click View

  2. Select Resource Sheet

Enter your resources:

Resource NameTypeMax Units
Mason TeamWork100%
Electrician TeamWork100%
Plumbing TeamWork100%
Site EngineerWork100%
Concrete CrewWork100%

Meaning of Max Units

ValueMeaning
100%One team
200%Two identical teams
300%Three identical teams

Example:

If you have 3 masonry crews:

Resource NameMax Units
Mason Team300%

Step 2: Return to Gantt Chart

  1. Click View

  2. Select Gantt Chart


Step 3: Insert Resource Names Column

  1. Right-click any column header

  2. Click Insert Column

  3. Choose Resource Names

Now you can assign resources directly to tasks.

Example:

Task NameDurationResource Names
Excavation3 DaysConcrete Crew
Brickwork GF5 DaysMason Team
Electrical Conduit2 DaysElectrician Team

Step 4: Assign Resources Using Assign Resources Tool

  1. Select a task

  2. Go to Resource tab

  3. Click Assign Resources

A window appears showing all resources.

Select:

  • Mason Team

  • Electrician Team

  • Site Engineer

Click Assign


Step 5: Assign Multiple Resources to One Task

Example:

TaskResources
Reinforcement WorkSteel Crew, Site Engineer
Concrete PouringConcrete Crew, Site Engineer
Final InspectionSite Engineer, Client

Microsoft Project allows several resources on one task.


Step 6: Check Resource Usage

Go to:

View → Resource Usage

You can see:

ResourceDay 1Day 2Day 3
Mason Team8h8h8h
Electrician Team4h8h4h

This helps identify overloaded crews.


Step 7: Check for Overallocation

Go to:

View → Resource Sheet

If a resource is overloaded, Microsoft Project displays a red indicator.

Example:

ResourceStatus
Mason Team🔴 Overallocated

This means the same team has been assigned to too many tasks at the same time.


Step 8: Verify Daily Workload

For construction projects, always check:

View → Team Planner (Project Professional)

or

View → Resource Usage

Look for:

✅ Balanced daily workload

❌ One day with too many tasks

❌ One day with no work


Construction Example

Resources

ResourceMax Units
Mason Team200%
Electrician Team100%
Plumbing Team100%
Site Engineer100%

Tasks

TaskDurationResource
Foundation5dConcrete Crew
Ground Floor Brickwork6dMason Team
Mezzanine Brickwork6dMason Team
Electrical Conduit3dElectrician Team
Plumbing Pipe Installation3dPlumbing Team

If Ground Floor Brickwork and Mezzanine Brickwork occur at the same time and there is only 100% Mason Team, Microsoft Project will show an overallocation.

Solutions:

  1. Increase Mason Team to 200%

  2. Split into Mason Team A and Mason Team B

  3. Use Resource Leveling

  4. Change task sequence


Best Practice for Sarim's Construction Projects

For your residential projects (12m²–50m² per floor), create resources by crew/team, not by individual worker:

  • Mason Team

  • Reinforcement Team

  • Formwork Team

  • Concrete Team

  • Plumbing Team

  • Electrical Team

  • Ceiling Team

  • Tile Team

  • Painting Team

  • Site Engineer

This makes scheduling, resource balancing, and resource leveling much easier and more realistic for a general contractor.

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level
```html ```