Simple Material Tracking System in Microsoft Project

Words: ...
↓ Quick Down

 🏡You can use Microsoft Project to track construction materials like cement, steel, bricks, tiles, doors, windows, equipment, and delivery schedules by combining:

  • Tasks (What work is happening)

  • Resources (What materials are needed)

  • Timeline (When materials are needed)

  • Cost Tracking (How much material costs)

  • Responsibility (Who controls it)

For a General Contractor like you, this becomes a simple Material Control System.


Simple Material Tracking System in Microsoft Project

1. Create Material Resources

In Microsoft Project:

Go to:

View → Resource Sheet

Add materials like this:

Material NameTypeMaterial LabelStd Rate
CementMaterialbag$5
Rebar D12Materialpcs$12
SandMaterial$18
Tiles 60x60Materialbox$25

Meaning of Each Column

Type = Material

This tells Microsoft Project:

“This is not a worker.”
“This is a consumable material.”


Material Label

Unit of measurement:

  • bag

  • kg

  • pcs

  • box

Example:

Cement = bag
Steel = ton
Sand = m³

Std Rate

Cost per unit.

Example:

1 bag cement = $5

Then Microsoft Project automatically calculates:

Quantity × Rate = Total Cost

2. Create Construction Tasks

Example:

Task Name
Foundation
Column Concrete
Brick Wall
Floor Tile

3. Assign Materials to Tasks

Go to:

Task → Assign Resources

Example:

TaskMaterialQuantity
FoundationCement120 bags
FoundationRebar D12300 pcs
Brick WallBrick5000 pcs

How Quantity Works

In Microsoft Project:

120 bags
300 pcs
20 m³

These are called:

Material Consumption

Microsoft Project will automatically:

  • Calculate total cost

  • Track usage

  • Show overloads

  • Show timing of material needs


4. Track Delivery Dates

Create separate delivery tasks.

Example:

Task
Deliver Cement
Deliver Steel
Deliver Tiles

Then connect them to construction work.

Example:

Deliver Cement → Foundation Concrete

This helps you know:

Material must arrive BEFORE work starts.


5. Use Gantt Chart for Material Timeline

The Microsoft Project Gantt Chart helps you see:

  • When material is needed

  • Which week materials arrive

  • Which activities consume materials

  • Delays caused by late delivery


6. Track Actual Material Usage

During construction:

Update:

PlannedActual
120 bags135 bags

This helps detect:

  • Waste

  • Theft

  • Rework

  • Poor estimation


7. Use Baseline for Comparison

Set baseline:

Project → Set Baseline

Then compare:

PlannedActual
CostReal Cost
QuantityActual Quantity
ScheduleReal Delivery

This is very important for contractors.


Best Setup for Construction Contractors

Recommended Structure

CategoryExample
TaskConcrete Work
Labor ResourceWorkers
Material ResourceCement
Cost ResourceTransport
MilestoneMaterial Approved

Example Real Construction Workflow

Foundation Work

Tasks

IDTask
1Order Cement
2Deliver Cement
3Foundation Concrete

Resources

ResourceQuantity
Cement120 bags
Sand15 m³
Steel300 pcs

Result

Microsoft Project can show:

  • Material cost

  • Delivery schedule

  • Consumption timing

  • Delayed delivery impact

  • Budget variance


Advanced Method (Professional GC System)

Large contractors often add:

Custom Columns

Example:

Material Status
Ordered
Delivered
Installed
Shortage

RACI Material Control

You asked earlier about RACI.

You can combine it like this:

TaskResponsible
Order CementProcurement
Receive CementStorekeeper
Approve UsageSite Engineer
Verify QuantityQS

This creates a professional Material Control SOP.


Recommended Views

In Microsoft Project use:

ViewPurpose
Gantt ChartSchedule
Resource SheetMaterial List
Resource UsageConsumption
Tracking GanttPlanned vs Actual
Team PlannerResponsibility

Most Important Idea

Microsoft Project is not only for schedule.

For contractors, it becomes:

TIME + MATERIAL + COST + RESPONSIBILITY CONTROL

That is why professional construction companies use it for:

  • Procurement tracking

  • Material delivery

  • Site control

  • Cost control

  • Delay prevention

  • Resource planning

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level