SUBMISSION PLAN
Project: ONE KMH TOWER
Date: 26th Dec 19
Location: ONE KMH Site Office, KMH Industrial Park I, Chom
Chao
Discipline: STRUCTURE
|
Item |
List of Document |
Submission Date |
|
1 |
EXCAVATION
WORK
Method statement of
sheet pile work
Shop drawing of
sheet pile and its specification
Instrumentation and
monitoring plan/method statements |
|
|
2 |
PILE
AND PILE TEST
Method statement of
cutting of pile head |
|
|
3 |
BASEMENT
AND GROUND FLOOR
Method Statement of
Waterproofing Work + supplier +materials
Concrete Mix Design
Reinforcement bar
specifications
Method Statement of
RC Work (column, slab, beam, pile cap)
Formwork Shop
Drawing, Scaffolding Shop Drawing and Calculation
Casting
sequence/construction joints of the basement slab/walls
Casting
sequence/construction joints of the ground floor slab
Shop Drawing of
Waterproofing
Shop drawing of
pile caps
Shop drawing of
water tank
Method Statement of
Soil Compaction
Shop drawing of
basement slab
Shop drawing of
basement wall
Shop drawing of
columns
Shop drawing of
core wall
Shop drawing of
ground floor slab
Shop drawing of
ground floor beam
Method Statement of
Anti-termite Treatment
Material samples: Waterproof product,
polystyrene, Waterstop
|
|