Why Does Creating a Project Schedule Take So Long for a 3-Story Townhouse?

Words: ...
↓ Quick Down

Why Does Creating a Project Schedule Take So Long for a 3-Story Townhouse?

Many engineers and contractors spend too much time creating a project schedule, even for a relatively small project such as a 3-story townhouse measuring 4.5m × 16m.

The problem is usually not the software. The problem is often the scheduling process itself.

1. The Work Breakdown Structure (WBS) Is Too Detailed

One common mistake is breaking the project into too many small tasks.

Example:

❌ Too Detailed

  • Column C1 Rebar

  • Column C1 Formwork

  • Column C1 Concrete

  • Column C2 Rebar

  • Column C2 Formwork

  • Column C2 Concrete

If a project has 20 columns, the schedule can quickly grow into dozens of unnecessary tasks.

✅ Better Approach

  • Ground Floor Columns

  • First Floor Columns

  • Second Floor Columns

Keep the schedule focused on management, not individual construction activities.


2. No Standard Schedule Template

Many contractors create a new schedule from scratch for every project.

This wastes a significant amount of time.

A standard template should include:

  • Pre-Construction

  • Foundation

  • Ground Floor Structure

  • First Floor Structure

  • Second Floor Structure

  • Roofing

  • MEP Works

  • Finishing Works

  • External Works

  • Handover

Using a template allows you to reuse proven structures and logic.


3. Estimating Duration Manually

Many planners spend hours guessing task durations.

Questions like:

  • Brickwork = 5 days?

  • Brickwork = 7 days?

  • Brickwork = 8 days?

Instead, use productivity rates.

Example:

  • Brickwork = 15 m²/day/team

  • Plastering = 25 m²/day/team

  • Tiling = 20 m²/day/team

Once the quantities are known, the duration can be calculated quickly and consistently.


4. Resource Planning Is Not Clear

Scheduling becomes difficult when resource availability is unknown.

Before creating the schedule, identify:

  • Number of masons

  • Number of carpenters

  • Number of steel workers

  • Number of electricians

  • Number of plumbers

Clear resource planning leads to more accurate durations.


5. Too Many Task Relationships

Some schedules contain hundreds of unnecessary links.

Example:

Task 1 → Task 2 → Task 3 → Task 4 → Task 5

While relationships are important, not every task requires a strict Finish-to-Start (FS) connection.

Consider using:

  • Start-to-Start (SS)

  • Finish-to-Finish (FF)

when appropriate to simplify the network and improve schedule flexibility.


6. Trying to Create a Perfect Schedule

Many planners believe that more detail means better control.

In reality, excessive detail often creates confusion.

Recommended Task Count

Schedule TypeNumber of Tasks
Executive Schedule20–30
Site Control Schedule50–100
Detailed Schedule100–150

For a 3-story townhouse, more than 200 tasks is usually unnecessary.


7. No Historical Project Library

Experienced contractors build a scheduling library over time.

This library includes:

  • Standard WBS

  • Standard Durations

  • Standard Resources

  • Standard Relationships

Instead of creating everything from scratch, they simply copy the template and make small adjustments.


Recommended Schedule Structure for a 3-Story Townhouse (4.5m × 16m)

  1. Pre-Construction

  2. Site Preparation

  3. Foundation Works

  4. Ground Floor Structure

  5. First Floor Structure

  6. Second Floor Structure

  7. Roof Structure

  8. Masonry Works

  9. MEP Rough-In

  10. Plastering Works

  11. Ceiling Works

  12. Floor Tiling

  13. Doors & Windows

  14. Painting Works

  15. Fixture Installation

  16. Testing & Commissioning

  17. Final Cleaning

  18. Project Handover

This structure is usually sufficient for effective project control and communication.


Key Lesson

A good schedule is not the one with the most tasks. A good schedule is the one that is easy to understand, easy to update, and easy to control.

Successful contractors do not create schedules from scratch every time. They build systems, templates, and standards that allow them to plan faster, manage better, and deliver projects more efficiently.

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level
```html ```