SOP: Daily Workload Balancing in Microsoft Project

Words: ...
↓ Down

SOP: Daily Workload Balancing in Microsoft Project

Purpose

To create a realistic construction schedule where daily work is distributed evenly, avoiding days with too much work and days with too little work.


1. Define the Project Scope

Before balancing workloads, ensure all project work is listed.

Example

Project: 2-Story House

  • Site Preparation

  • Foundation

  • Ground Floor Structure

  • First Floor Structure

  • Brickwork

  • Electrical

  • Plumbing

  • Finishing

  • Handover

✅ A complete scope creates a more accurate workload distribution.


2. Break Work into Small Tasks

Avoid large tasks such as:

❌ Brickwork – 30 Days

Instead:

✅ Ground Floor Brickwork – 10 Days

✅ Mezzanine Brickwork – 10 Days

✅ First Floor Brickwork – 10 Days

Smaller tasks make balancing easier.


3. Create Logical Task Relationships

Link activities correctly.

Example:

TaskPredecessor
FoundationSite Preparation
ColumnsFoundation
BeamsColumns
SlabBeams

Use:

  • Finish-to-Start (FS)

  • Start-to-Start (SS)

  • Finish-to-Finish (FF)

Avoid unnecessary constraints.


4. Assign Resources Correctly

Assign each task to the correct crew.

Example:

TaskResource
ExcavationEarthwork Team
ConcreteMason Team
BrickworkMason Team
ElectricalElectrician Team
PlumbingPlumbing Team

Avoid assigning every task to one resource.


5. Check Resource Overallocation

Resource Sheet

View → Resource Sheet

Look for:

🔴 Red Resource Names

These indicate overallocation.

Example:

ResourceStatus
Mason TeamOverallocated
ElectricianNormal

6. Use Resource Usage View

View → Resource Usage

This is the most important view for workload balancing.

It shows:

  • Daily Work Hours

  • Weekly Work Hours

  • Resource Overloads

Example:

DateMason Team
Monday8h
Tuesday24h 🔴
Wednesday6h

Tuesday is overloaded.


7. Split Large Activities

Instead of:

Brickwork = 20 Days

Split into:

  • Brickwork Area A

  • Brickwork Area B

  • Brickwork Area C

Benefits:

✅ Better control

✅ Easier balancing

✅ Easier tracking


8. Adjust Task Timing

Move non-critical tasks.

Example:

Before

Monday

  • Brickwork

  • Electrical

  • Plumbing

  • Ceiling

Total = 4 Crews

After

Monday

  • Brickwork

  • Electrical

Tuesday

  • Plumbing

  • Ceiling

Result:

✅ Balanced workload


9. Use Resource Leveling Carefully

Resource → Leveling Options

Recommended Settings:

  • Level only within available slack

  • Manual leveling

  • Day by day

Then:

Resource → Level All

Microsoft Project will delay tasks to remove overloads.

Important

Always save a Baseline before leveling.

Otherwise:

❌ Schedule may change unexpectedly.


10. Review Critical Path After Leveling

Sometimes leveling changes project duration.

Go to:

Format → Critical Tasks

Review:

  • New Critical Activities

  • New Finish Date

  • Added Delays

Never assume leveling is correct without checking.


11. Balance by Crew, Not Only by Task

Construction schedules should balance crews.

Example:

Mason Team

DayWork
Monday8h
Tuesday8h
Wednesday8h

Good

Mason Team

DayWork
Monday20h
Tuesday0h
Wednesday4h

Bad

Goal:

✅ Stable daily workload


12. Review Daily Workload Using Timescale

View → Resource Usage

Right-click Timescale

Select:

  • Days

Review every day.

Look for:

  • Empty days

  • Overloaded days

  • Crew conflicts


Construction Best Practice

For residential projects like your 8AM Contractor projects:

Target Crew Utilization

  • 70%–90% utilization = Good

  • Above 100% = Overloaded

  • Below 50% = Underutilized

Keep crews working consistently rather than alternating between extremely busy and idle days.


Daily Workload Balancing Checklist

Before finalizing your schedule:

☐ All tasks defined

☐ WBS completed

☐ Resources assigned

☐ Resource Usage reviewed

☐ Overallocations removed

☐ Large tasks split

☐ Resource Leveling performed

☐ Critical Path reviewed

☐ Daily workload checked

☐ Baseline saved

Key Principle

A good Microsoft Project schedule is not the one that finishes earliest. It is the one that can actually be executed by the available crews every day without overloading or leaving them idle.

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level
```html ```