SOP: Assign Durations in Microsoft Project

Words: ...
↓ Quick Down

SOP: Assign Durations in Microsoft Project

Purpose

Assign accurate task durations so the project schedule is realistic, balanced, and achievable.


Step 1: Create the Task List

Before assigning durations, create all project tasks.

Example:

IDTask Name
1Site Survey
2Excavation
3Rebar Installation
4Concrete Pouring
5Brickwork
6Painting

Rule:

  • One task = One clear activity.

  • Do not combine multiple activities into one task.

❌ "Excavation + Rebar + Concrete"

✅ "Excavation"
✅ "Rebar Installation"
✅ "Concrete Pouring"


Step 2: Estimate Work Quantity

Determine how much work must be completed.

Example:

TaskQuantity
Excavation50 m³
Brickwork100 m²
Painting500 m²

Duration should be based on quantity, not guessing.


Step 3: Determine Productivity Rate

Find how much work the crew can complete per day.

Example:

TaskDaily Productivity
Excavation10 m³/day
Brickwork20 m²/day
Painting100 m²/day

Step 4: Calculate Duration

Formula:

\text{Duration} = \frac{\text{Work Quantity}}{\text{Daily Productivity}}

Example:

Excavation:

  • Quantity = 50 m³

  • Productivity = 10 m³/day

Duration:

50 ÷ 10 = 5 Days


Step 5: Enter Duration in Microsoft Project

In the Duration column, enter:

TaskDuration
Site Survey2d
Excavation5d
Rebar Installation3d
Concrete Pouring1d
Brickwork5d
Painting5d

Common Units:

UnitMeaning
mMinutes
hHours
dDays
wWeeks
moMonths

Examples:

  • 8h = 8 Hours

  • 5d = 5 Days

  • 2w = 2 Weeks

  • 1mo = 1 Month


Step 6: Use Milestones Correctly

Milestones have no duration.

Enter:

0d

Examples:

TaskDuration
Contract Signed0d
Design Approved0d
Project Handover0d

Remember:

  • Tasks = Work

  • Milestones = Events


Step 7: Review Resource Capacity

Check whether the duration is achievable.

Example:

If Brickwork requires:

  • 100 m²

  • Crew productivity = 20 m²/day

Then:

  • 5 Days = Realistic

But:

  • 2 Days = Unrealistic

Always verify with actual site productivity.


Step 8: Add Contingency When Necessary

For risky activities, add reasonable buffer.

Examples:

TaskNormalPlanned
Excavation5d6d
Painting5d6d

Reasons:

  • Rain

  • Material delays

  • Equipment breakdown

  • Labor shortages


Step 9: Check the Schedule Logic

After entering durations:

  1. Create task relationships (FS, SS, FF, SF).

  2. Review the Gantt Chart.

  3. Look for unrealistic durations.

  4. Verify Critical Path activities.

  5. Adjust durations if necessary.


Best Practice for Construction Projects

  1. Define task clearly.

  2. Measure work quantity.

  3. Calculate productivity.

  4. Assign realistic duration.

  5. Link tasks correctly.

  6. Review resource availability.

  7. Add contingency for risks.

  8. Update actual durations during construction.

Golden Rule

Do not guess task durations.

Use:

Quantity + Productivity + Experience = Accurate Duration

This creates a schedule that is easier to manage, easier to track, and more likely to finish on time.

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level
```html ```