Resource Sheet: Define Construction Crews in Microsoft Project

Words: ...
↓ Down

Resource Sheet: Define Construction Crews in Microsoft Project

Why Resource Sheet Matters

Many construction schedules fail because tasks are planned without considering the actual availability of crews.

A schedule may show:

  • Foundation Work

  • Rebar Work

  • Formwork Work

  • Masonry Work

  • Electrical Work

All starting at the same time.

However, in reality, you may only have:

  • 1 Rebar Team

  • 1 Formwork Team

  • 1 Mason Team

  • 1 Electrician Team

When the schedule ignores crew availability, it creates:

  • Resource conflicts

  • Delays

  • Overloaded teams

  • Unrealistic completion dates

The purpose of the Resource Sheet in Microsoft Project is to define your construction crews and allow Microsoft Project to calculate workload automatically.


What is a Resource Sheet?

A Resource Sheet is a database of all resources available to your project.

Resources can include:

Labor Resources

  • Mason Team

  • Rebar Team

  • Formwork Team

  • Electrician Team

  • Plumbing Team

  • Painting Team

Equipment Resources

  • Excavator

  • Crane

  • Concrete Mixer

  • Scaffolding

Material Resources

  • Cement

  • Sand

  • Rebar

  • Brick

For construction scheduling, labor crews are usually the most important resources.


Step 1: Open Resource Sheet

Open Microsoft Project.

Navigate to:

View → Resource Sheet

You will see a table containing:

Resource NameTypeMax Units

This is where all crews will be created.


Step 2: Create Construction Crews

Enter each team as a Work Resource.

Example:

Resource NameType
Mason TeamWork
Rebar TeamWork
Formwork TeamWork
Electrician TeamWork
Plumbing TeamWork
Painting TeamWork

These represent actual crews available on site.


Step 3: Set Max Units

Max Units represent crew availability.

Example

Resource NameMax Units
Mason Team100%

This means:

One Mason Team is available.


Multiple Crews

If you have:

  • Crew A

  • Crew B

  • Crew C

Then:

Resource NameMax Units
Mason Team300%

Microsoft Project understands that three masonry crews can work simultaneously.


Common Examples

Resource NameMax Units
Rebar Team200%
Formwork Team300%
Electrician Team100%
Plumbing Team100%

Step 4: Define Crew Composition

Each crew should have a standard structure.

Example:

Mason Team

  • 1 Foreman

  • 6 Masons

  • 2 Helpers

Rebar Team

  • 1 Foreman

  • 5 Steel Fixers

  • 2 Helpers

Formwork Team

  • 1 Foreman

  • 8 Carpenters

  • 2 Helpers

Electrician Team

  • 1 Supervisor

  • 4 Electricians

Store this information in the Notes field for future reference.


Step 5: Assign Crews to Tasks

After creating resources, switch back to:

View → Gantt Chart

Assign crews to construction activities.


Example

TaskResource
Foundation RebarRebar Team
Foundation FormworkFormwork Team
Foundation ConcreteConcrete Team
Ground Floor BrickworkMason Team
Electrical ConduitElectrician Team

Now Microsoft Project knows which team performs each activity.


Step 6: Check Resource Usage

Navigate to:

View → Resource Usage

This view shows:

  • Which crew is assigned

  • How much work they have

  • When they are scheduled

Example:

Mason Team

  • GF Brickwork

  • 1F Brickwork

  • Staircase Brickwork

You can immediately see workload distribution.


Step 7: Identify Overallocated Crews

Suppose:

Mason Team

Assigned to:

  • Ground Floor Brickwork

  • First Floor Brickwork

Both start on the same day.

Since only one Mason Team exists, Microsoft Project will flag the resource as:

Overallocated

This means the schedule is unrealistic.


Step 8: Use Resource Leveling

Navigate to:

Resource → Level All

Microsoft Project will automatically:

  • Delay conflicting tasks

  • Balance crew workloads

  • Reduce resource conflicts

Example:

Before Leveling:

TaskStart
GF BrickworkDay 1
1F BrickworkDay 1

Conflict occurs.

After Leveling:

TaskStart
GF BrickworkDay 1
1F BrickworkDay 8

No conflict.


Recommended Crew Structure for Residential Construction

For a typical house project:

Resource Name
Mason Team
Rebar Team
Formwork Team
Concrete Team
Electrician Team
Plumbing Team
Ceiling Team
Tiling Team
Painting Team
Aluminum Team
Cleaning Team

Recommended Crew Structure for 8AM Contractor

Resource NameMax Units
Mason Team100%
Rebar Team100%
Formwork Team100%
Concrete Team100%
Electrician Team100%
Plumbing Team100%
Finishing Team100%
Painting Team100%

For larger projects:

Resource NameMax Units
Mason Team300%
Rebar Team200%
Formwork Team200%
Electrician Team100%

Key Principle

A professional schedule is not just about Tasks and Dates.

A professional schedule must answer three questions:

What needs to be done?

Tasks

When should it be done?

Schedule

Who will do it?

Resources

The Resource Sheet is the place where Microsoft Project learns who is available to perform the work. Without properly defining crews, the schedule may look good on paper but fail in the real world. By defining Mason Teams, Rebar Teams, Formwork Teams, and Electrician Teams in the Resource Sheet, you create a realistic, achievable, and resource-balanced construction schedule.

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level
```html ```