Microsoft Project Construction Workflow

Words: ...
↓ Down

 For a construction company like 8AM Contractor, the best way to use Microsoft Project is to follow a complete workflow from project start to project completion.

Microsoft Project Construction Workflow

Client Award Project
         │
         ▼
1. Project Setup
         │
         ▼
2. Create WBS
         │
         ▼
3. Create Schedule
         │
         ▼
4. Define Resources
         │
         ▼
5. Assign Resources
         │
         ▼
6. Estimate Costs
         │
         ▼
7. Baseline Project
         │
         ▼
8. Execute Construction
         │
         ▼
9. Update Progress
         │
         ▼
10. Resource Leveling
         │
         ▼
11. Cost & Schedule Control
         │
         ▼
12. Reporting
         │
         ▼
13. Project Closeout

1. Project Setup

Input:

  • Contract

  • Scope of Work

  • Drawings

  • BOQ

  • Specifications

Example:

Project Name:
4-Storey Commercial Building

Start Date:
01-Jul-2026

Calendar:
Monday–Saturday


2. Create WBS (Work Breakdown Structure)

Example:

1. Pre-Construction

2. Foundation
   2.1 Excavation
   2.2 Lean Concrete
   2.3 Footing Reinforcement
   2.4 Footing Concrete

3. Ground Floor
   3.1 Column
   3.2 Beam
   3.3 Slab

4. First Floor
5. Second Floor
6. Roof
7. Finishing
8. Handover

Microsoft Project View:

Summary Task
    Sub Task
       Activity

3. Create Schedule

Input duration for every task.

Example:

TaskDuration
Excavation5 Days
Lean Concrete2 Days
Rebar Work4 Days
Concrete Casting1 Day

4. Link Activities

Create logical relationships.

Excavation
      ↓
Lean Concrete
      ↓
Rebar Work
      ↓
Concrete Casting

Use:

FS = Finish to Start

Example:

Excavation → FS → Lean Concrete

This creates the Critical Path.


5. Define Resources

Resource Sheet:

Resource NameType
Mason TeamWork
Rebar TeamWork
Formwork TeamWork
Electrician TeamWork
ExcavatorWork
Concrete PumpWork

For 8AM Contractor:

Mason Team
Rebar Team
Formwork Team
Electrical Team
Plumbing Team
Finishing Team

6. Assign Resources

Example:

TaskResource
Rebar WorkRebar Team
FormworkFormwork Team
Concrete CastingMason Team

Microsoft Project automatically calculates:

  • Work Hours

  • Resource Loading

  • Manpower Requirement


7. Estimate Cost

Resource Rates:

ResourceRate
Mason Team$50/day
Rebar Team$45/day
Excavator$80/day

Project automatically calculates:

Cost = Work × Rate

Example:

Cost=Work\times Rate


8. Baseline Project

Before construction starts:

Project → Set Baseline

Save:

  • Planned Start

  • Planned Finish

  • Planned Cost

This becomes your target.


9. Execute Construction

On site:

Foundation Complete = 100%
Column Complete = 50%
Beam Complete = 20%

Update every week.


10. Resource Leveling

Find overallocated crews.

Example:

Rebar Team
   Floor 1
   Floor 2
   Roof

All scheduled simultaneously.

Problem:

Overallocated

Solution:

Resource → Level Resources

Microsoft Project balances workloads automatically.


11. Cost & Schedule Control

Compare:

PlannedActual
50%40%

Result:

Behind Schedule

Check:

  • Critical Path

  • Variance

  • Cost Overrun

Useful Views:

  • Tracking Gantt

  • Resource Usage

  • Team Planner


12. Weekly Reporting

Every Monday meeting:

Report:

Planned Progress
Actual Progress
Delay
Resource Status
Cost Status
Critical Activities

Export:

  • PDF

  • Excel

  • Print Schedule


13. Project Closeout

Final:

100% Complete

Deliver:

  • As-Built Drawings

  • Handover Documents

  • Defect List

  • Final Cost Report


Practical Workflow for 8AM Contractor

Drawings + BOQ
        ↓
Create WBS
        ↓
Create Schedule
        ↓
Assign Crews
        ↓
Calculate Cost
        ↓
Baseline
        ↓
Construction Start
        ↓
Weekly Update
        ↓
Resource Leveling
        ↓
Progress Control
        ↓
Client Report
        ↓
Project Completion

For a contractor, about 80% of daily work in Microsoft Project is usually focused on:

  1. WBS Creation

  2. Activity Linking

  3. Resource Assignment

  4. Weekly Progress Update

  5. Resource Leveling

  6. Tracking Gantt Review

  7. Client Reporting

Master these seven activities, and you can manage most building projects effectively in Microsoft Project.

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level
```html ```