How to Change Baseline in Microsoft Project

Words: ...
↓ Down

📌 How to Change Baseline in Microsoft Project

A Baseline is a snapshot of your approved project schedule. It stores the planned Start, Finish, Duration, Work, and Cost so you can compare them against actual project performance.


🎯 Method 1: Change the Entire Project Baseline

Use this when the entire schedule has been revised.

Steps

  1. Go to Project tab.

  2. Click Set Baseline.

  3. Select Set Baseline.

  4. Choose Baseline (or Baseline 1–10).

  5. Select Entire Project.

  6. Click OK.

⚠️ Warning: This will overwrite the selected baseline.


🎯 Method 2: Change Baseline for Selected Tasks Only

Use this when only certain activities have changed.

Steps

  1. Select the tasks to update.

  2. Go to Project → Set Baseline.

  3. Select Set Baseline.

  4. Choose the desired baseline.

  5. Select Selected Tasks.

  6. Enable:

    • ✅ Roll up baselines to all summary tasks

    • ✅ From subtasks into selected summary tasks (if needed)

  7. Click OK.

Benefits

  • Updates only affected tasks.

  • Keeps the rest of the project baseline unchanged.

  • Useful for change orders and approved variations.


🎯 Method 3: Preserve the Original Baseline

Microsoft Project provides multiple baseline slots:

  • Baseline

  • Baseline 1

  • Baseline 2

  • Baseline 3

  • ...

  • Baseline 10

Example

BaselinePurpose
BaselineOriginal approved schedule
Baseline 1Revision #1
Baseline 2Revision #2
Baseline 3Revision #3

Steps

  1. Go to Project → Set Baseline.

  2. Choose Baseline 1 (or another available baseline).

  3. Select Entire Project.

  4. Click OK.

✅ This preserves the original project commitment while tracking revisions.


📊 How to View Baseline Information

Insert Baseline Columns

  1. Right-click a column header.

  2. Select Insert Column.

  3. Add:

    • Baseline Start

    • Baseline Finish

    • Start Variance

    • Finish Variance

What They Show

FieldMeaning
Baseline StartOriginal planned start date
Baseline FinishOriginal planned finish date
Start VarianceDifference between planned and current start
Finish VarianceDifference between planned and current finish

🏗️ Construction Best Practice

✅ Set Baseline After Approval

Only set the baseline after:

  • Scope is finalized.

  • Schedule is reviewed.

  • Client approval is received.

✅ Keep Original Baseline

Avoid overwriting the original baseline whenever possible.

✅ Use Additional Baselines for Revisions

When schedule changes occur:

  • Original Schedule → Baseline

  • Revision 1 → Baseline 1

  • Revision 2 → Baseline 2

  • Revision 3 → Baseline 3

✅ Monitor Schedule Performance

Compare:

  • Baseline Dates

  • Current Dates

  • Actual Progress

This helps identify:

  • Delays

  • Schedule recovery

  • Impact of changes

  • Project performance


💡 Simple Way to Remember

📸 Baseline = Original Plan

📅 Current Schedule = Today's Plan

📊 Variance = Difference Between Them

Without a baseline, you cannot accurately measure whether your project is ahead, behind, or on schedule.

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level
```html ```