SOP: Step by Step to Create a Schedule in Microsoft Project

Words: ...
↓ Quick Down

SOP: Step by Step to Create a Schedule in Microsoft Project

1. Create New Project

Open Microsoft Project → click Blank Project.

2. Set Project Start Date

Go to ProjectProject Information → set Start Date.

3. Set Working Time

Go to ProjectChange Working Time.
Set working days, holidays, and working hours.

4. Add Main Work Sections

Create big tasks first, for example:

  1. Mobilization

  2. Foundation Work

  3. Structural Work

  4. Masonry Work

  5. MEP Work

  6. Finishing Work

  7. Handover

5. Break Down Tasks

Under each main section, add smaller tasks.

Example:

Foundation Work

  • Excavation

  • Lean concrete

  • Rebar installation

  • Formwork

  • Concrete pouring

  • Curing

6. Create Summary Tasks

Select the small tasks → click Indent Task.
The main task becomes a summary task.

7. Add Duration

Enter duration for each task.

Example:

  • Excavation: 3 days

  • Rebar installation: 2 days

  • Concrete pouring: 1 day

8. Link Tasks

Select tasks in order → click Link Tasks.
This creates task dependency: one task starts after another finishes.

9. Add Milestones

Set duration to 0 days for important points.

Example:

  • Foundation Completed — 0 days

  • Roof Completed — 0 days

  • Project Handover — 0 days

10. Add Resources

Go to Resource Sheet and add:

  • Site Manager

  • Engineer

  • Workers

  • Subcontractor

  • Equipment

Then assign resources to tasks.

11. Check Critical Path

Go to Format → turn on Critical Tasks.
Critical tasks are tasks that can delay the whole project.

12. Save Baseline

After the schedule is approved:
Go to ProjectSet BaselineSet Baseline.

13. Update Progress Weekly

Every week, update:

  • % Complete

  • Actual Start

  • Actual Finish

  • Remaining Duration

14. Report Delay

Compare actual progress with baseline.
If delayed, adjust manpower, sequence, or working hours.

Simple Rule

Plan → Link → Check → Baseline → Update → Control. 
Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level