SOP — Request for Information (RFI)
A practical site-ready standard operating procedure for managing unclear, missing, or conflicting information before work execution.
1) Purpose
The purpose of this SOP is to ensure that all unclear, missing, inconsistent, or conflicting information is formally clarified before execution on site.
- Prevent rework
- Reduce delay risk
- Control cost and time
- Protect contractor responsibility with written record
- Improve communication between contractor, consultant, architect, and engineer
2) Scope
This SOP applies to all project personnel involved in reviewing drawings, specifications, site conditions, and technical coordination.
- Site Engineer
- Project Engineer
- Project Manager
- Document Controller
- Construction Manager
- Consultant / Designer coordination team
3) Definitions
| Term | Meaning |
|---|---|
| RFI | Request for Information — a formal question used to clarify project information before work proceeds. |
| RFI Register | A tracking log for all submitted RFIs, statuses, dates, and responses. |
| Open | RFI submitted but not yet answered or not yet implemented. |
| Closed | Response received, implemented, and properly recorded. |
4) Responsibilities
| Role | Responsibility |
|---|---|
| Site Engineer | Identify issue, collect evidence, draft the RFI, attach photo/sketch/reference. |
| Project Manager | Review wording, confirm technical accuracy, approve and submit. |
| Document Controller | Assign number, record in register, distribute and archive response. |
| Consultant / Engineer / Architect | Review the question and issue official clarification or instruction. |
| Site Team | Implement approved response and update execution accordingly. |
5) When to Issue an RFI
- Drawing is unclear
- Dimensions are missing
- Specifications are incomplete
- Two drawings conflict with each other
- Site condition differs from design condition
- Rebar, connection, level, or material detail is not shown
- Method of installation needs confirmation
6) RFI Workflow
Review drawing, specification, and site condition.
Write the question clearly and attach references.
Project Manager checks the draft before submission.
Send to consultant / architect / engineer.
Record in RFI Register as Open / Pending / Closed.
Get formal clarification or instruction.
Execute work according to approved reply.
Update register and file all supporting documents.
7) RFI Preparation Standard
Every RFI should contain the following:
- Project name
- RFI number
- Date
- Subject
- Reference drawing/specification
- Description of issue
- Clear request for clarification
- Suggested solution (recommended)
- Attachments: photo, sketch, marked-up drawing
- Requested response date
8) RFI Template
Project Name: ______________________ Project Location: ___________________ RFI No: _____________________________ Date: ______________________________ To: ________________________________ From: ______________________________ Company: ___________________________ Subject: ____________________________________ Reference: Drawing No: ________________________ Specification Section: ______________ Location / Area: ____________________ Description of Issue: ____________________________________ ____________________________________ ____________________________________ Request for Clarification: ____________________________________ ____________________________________ Suggested Solution (Recommended): ____________________________________ ____________________________________ Attachments: [ ] Photo [ ] Sketch [ ] Marked-up Drawing [ ] Other: _________________________ Requested Response Date: ____________ Prepared by: _______________________ Reviewed by: _______________________ Approved by: _______________________
9) RFI Register Format
| RFI No | Date | Subject | Sent To | Status | Reply Date | Action |
|---|---|---|---|---|---|---|
| RFI-001 | 26/03/2026 | Beam B1 Reinforcement Clarification | Structural Engineer | Open | - | Awaiting reply |
| RFI-002 | 26/03/2026 | Stair Landing Level Conflict | Architect | Closed | 27/03/2026 | Update layout drawing |
10) Response Time Control
- Standard response target: 2–5 working days, depending on urgency
- Urgent items affecting critical path should be highlighted immediately
- Follow up daily for high-impact RFIs
- Escalate overdue RFI to Project Manager and Consultant Representative
11) Site Rules for Good RFI Practice
Do
- Use clear and short sentences
- Refer to exact drawing number and area
- Attach marked-up image when possible
- Suggest a solution
- Track every RFI in the register
- Communicate urgent impact early
Do Not
- Use vague wording
- Send RFI without checking references first
- Delay the question until work is stopped
- Execute work based on assumption
- Forget to file the official response
12) Example of a Good RFI
Subject: Clarification of reinforcement for Beam B1 at Grid C-4
Reference: Structural Drawing S-12
Issue: Beam size is shown as 200x400 mm, but top and bottom reinforcement detail is not indicated.
Question: Please confirm required reinforcement arrangement for Beam B1 at Grid C-4.
Suggested Solution: Contractor proposes 4T16 top and 2T16 bottom bars, with stirrups T8-150 unless otherwise directed. Please confirm.
13) Final Management Principle
RFI is not just a question. It is a control system for project clarity, time, cost, documentation, and professional protection.