Start-to-Start (SS) in Microsoft Project

Words: ...
↓ Down

Start-to-Start (SS) in Microsoft Project

What is Start-to-Start (SS)?

SS stands for Start-to-Start.

A Start-to-Start relationship means:

The successor task cannot start until the predecessor task starts.

In simple terms:

Two tasks are linked by their start dates.

The tasks do not need to finish together, but they must start together (or the successor starts after the predecessor starts).


Simple Example

Predecessor TaskRelationshipSuccessor Task
Electrical InstallationSSCeiling Work

Explanation

When Electrical Installation starts, Ceiling Work can start.

For example:

TaskStart Date
Electrical InstallationMonday
Ceiling WorkMonday

The ceiling team can begin work after the electrical team has started installing conduits, cables, or supports.

Both activities can proceed at the same time.


Construction Example

Plumbing and Wall Construction

Predecessor TaskRelationshipSuccessor Task
Plumbing InstallationSSWall Construction

Explanation

Once plumbing installation begins, wall construction can also begin in areas where plumbing rough-ins have already been completed.

Both teams work simultaneously.


Real Site Example

Reinforcement and Formwork Inspection

Predecessor TaskRelationshipSuccessor Task
Rebar InstallationSSQuality Inspection

Explanation

The inspection team can start inspecting completed sections as soon as rebar installation starts, without waiting for the entire installation to finish.


When Should You Use SS?

Use Start-to-Start when:

  • Multiple teams can work simultaneously.

  • One task only needs another task to begin before it can start.

  • You want to shorten the project schedule.

  • Activities overlap naturally.


Benefits of SS Relationships

✅ Reduces project duration.

✅ Allows parallel work.

✅ Improves resource utilization.

✅ Speeds up project completion.

✅ Creates a more realistic construction schedule.


Comparison of Task Relationships

TypeFull WordMeaning
FSFinish-to-StartTask B starts after Task A finishes
SSStart-to-StartTask B starts after Task A starts
FFFinish-to-FinishTask B finishes after Task A finishes
SFStart-to-FinishTask B finishes after Task A starts

Construction Examples of SS

Structure Works

  • Column Casting → SS → Beam Reinforcement

MEP Works

  • Electrical Installation → SS → Ceiling Work

Interior Works

  • Tile Installation → SS → Grouting Preparation

Site Management

  • Construction Work → SS → Progress Monitoring

Procurement

  • Material Delivery → SS → Material Inspection


Easy Way to Remember

SS = Start Together

Think:

"Once the first task starts, the second task is allowed to start."

Example

  • Electrical Installation → SS → Ceiling Work

  • Plumbing Installation → SS → Wall Construction

  • Rebar Installation → SS → Inspection


Key Lesson

Start-to-Start (SS) means:

The successor task cannot start until the predecessor task has started.

This relationship is commonly used in construction projects when two activities can proceed in parallel, helping teams work more efficiently and reducing overall project duration.

Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level
```html ```