SOP: Resource Planning in Microsoft Project

Words: ...
↓ Quick Down

 

SOP: Resource Planning in Microsoft Project

1. Purpose

The purpose of Resource Planning in Microsoft Project is to:

  • Plan manpower, materials, equipment, and cost

  • Prevent overloading workers or machines

  • Ensure the right resources are available at the right time

  • Improve schedule accuracy

  • Control project productivity and budget


2. What is “Resource” in Microsoft Project?

A Resource means anything needed to complete a task.

There are 3 main types:

Resource TypeMeaningExample
Work ResourceHuman or machine workingEngineer, Carpenter, Excavator
Material ResourceConsumable materialCement, Sand, Steel
Cost ResourceExtra cost itemTransport, Fuel, Permit

3. Main Principle

Good Resource Planning =

Right Resource
+ Right Quantity
+ Right Time
+ Right Task
= Smooth Project Execution

4. Resource Planning Workflow

1. Create Tasks
        ↓
2. Create Resources
        ↓
3. Assign Resources
        ↓
4. Check Workload
        ↓
5. Balance Resources
        ↓
6. Monitor Actual Progress

5. Step-by-Step SOP

STEP 1 — Create Project Tasks

First create all activities:

Example:

Foundation Work
Column Work
Beam Work
Roof Work
Painting

STEP 2 — Open Resource Sheet

In Microsoft Project:

View → Resource Sheet

This is where you create all resources.


STEP 3 — Create Work Resources

Example:

Resource NameTypeMax UnitsStd Rate
Site EngineerWork100%$20/hr
Carpenter TeamWork300%$15/hr
ExcavatorWork100%$50/hr

Meaning of Max Units

ValueMeaning
100%1 person/machine
200%2 workers
300%3 workers

STEP 4 — Create Material Resources

Example:

Resource NameTypeMaterial Label
CementMaterialBags
RebarMaterialTons
SandMaterial

STEP 5 — Assign Resources to Tasks

Go to:

Task → Assign Resources

Example:

TaskResource
ExcavationExcavator
FormworkCarpenter Team
Rebar InstallationSteel Team

STEP 6 — Set Duration and Work

Microsoft Project automatically calculates:

Work = Duration × Units

Example:

Work = Duration \times Units

If:

Duration = 5 days
Units = 2 workers

Then:

Total Work = 10 worker-days

7. Resource Loading Concept

Example

Worker A
Monday      = 100%
Tuesday     = 150%
Wednesday   = 200%

This means the worker is overloaded.


8. Resource Overallocation

Meaning

Overallocation happens when:

One resource
is assigned too much work
at the same time.

Microsoft Project shows:

  • Red person icon

  • Red indicators


9. How to Fix Overallocated Resources

Method 1 — Resource Leveling

Go to:

Resource → Level Resource

Microsoft Project will:

  • Delay some tasks

  • Reduce conflicts

  • Balance workload


Method 2 — Add More Workers

Example:

Carpenter Team
100% → 300%

Method 3 — Split Tasks

Instead of:

One worker = 10 hours/day

Split into:

Two workers = 5 hours/day

10. Resource Usage View

Go to:

View → Resource Usage

You can see:

  • Daily workload

  • Overloaded days

  • Remaining availability


11. Team Planning Example

House Construction Example

TaskResourceDuration
ExcavationExcavator2 days
FoundationConcrete Team5 days
Rebar WorkSteel Team4 days
PaintingPainter Team3 days

12. Material Consumption Planning

Example:

TaskMaterialQuantity
Slab ConcreteCement300 bags
Beam WorkRebar2 tons

This helps:

  • Procurement planning

  • Stock control

  • Delivery scheduling


13. Cost Planning

Microsoft Project can calculate:

Labor Cost
+ Material Cost
+ Equipment Cost
= Total Project Cost

\text{Total Project Cost} = \text{Labor Cost} + \text{Material Cost} + \text{Equipment Cost}


14. Resource Planning Strategy for GC

For a 8AM General Contractor system:

Focus on:

A. Critical Workers

Identify:

  • Site engineer

  • Foreman

  • Skilled workers


B. Shared Equipment

Example:

1 Excavator
used by
3 project zones

Need scheduling coordination.


C. Material Delivery Timing

Avoid:

Too early = storage problem
Too late = schedule delay

15. Best Practice SOP

Daily

  • Check worker availability

  • Check equipment usage

  • Update actual progress


Weekly

  • Review resource workload

  • Check overallocations

  • Update manpower forecast


Monthly

  • Compare planned vs actual cost

  • Analyze productivity

  • Improve future planning


16. Important Microsoft Project Views

ViewPurpose
Gantt ChartTimeline
Resource SheetResource database
Resource UsageWorkload
Team PlannerVisual resource planning
Task UsageResource by task

17. Common Mistakes

MistakeResult
No resource assignmentFake schedule
Too many tasks for one workerBurnout
Ignore material planningSite delays
No actual updatesWrong forecast

18. Golden Rule

Tasks tell WHAT to do
Schedule tells WHEN to do
Resources tell WHO and HOW to do

19. Final Construction Management Concept

Strong Schedule
without Resource Planning
=
Weak Execution

But:

Good Resource Planning
=
Stable Site Operation
+ Better Productivity
+ Better Profit
+ Less Delay
Previous Post Next Post
🕒
Color
Font
19
Content
Outline Data
Outline Level