SOP: Beam & Slab Construction (Site Execution)
A practical site workflow for GC teams: Formwork → Rebar → Inspection → Casting → Curing.
Purpose
Ensure safety, quality, and correct sequence for RC beam & slab works on site.
Scope
Formwork, rebar fixing, inspection, concrete casting, curing, stripping, QA & safety.
Responsible
Site Engineer • Foreman • Rebar Team • Formwork Team • Concrete Team • QA/QC • Structural Engineer (approval).
Easy Rule
Drawings → Formwork → Beam Rebar → Slab Rebar → Inspection → Concrete → Curing
1
Pre-Construction Preparation
Confirm drawings, materials, and site readiness before any formwork starts.
Pre-Construction Preparation
Confirm drawings, materials, and site readiness before any formwork starts.
1.1 Drawing & Design Check
- Review structural drawings: beam sizes, slab thickness, rebar details, bar marks.
- Confirm span & support type (simply supported / continuous / cantilever).
- Verify concrete grade & steel grade per spec.
- Confirm standard/code used (ACI / BS / local project spec).
1.2 Material Check
- Rebar diameter, grade, and delivery certificates (if required).
- Formwork: plywood/steel panels, props, bracing, clamps.
- Concrete supply: mix design, slump requirement, truck access.
- Accessories: chairs, spacers, cover blocks, tie wire.
Site Tip: Prepare a “pour day plan” (truck route, pump location, vibrator quantity, manpower).
2
Setting Out & Level Control
Mark beam lines, slab boundaries, and control levels accurately.
Setting Out & Level Control
Mark beam lines, slab boundaries, and control levels accurately.
- Mark beam centerlines and slab edges from grid/architectural reference.
- Check beam width & depth against drawings.
- Set slab top level (reference: ±0.00) and check tolerance.
- Confirm openings (stairs, ducts, sleeves) are located correctly.
QC Point: Fix any level error now—later it becomes expensive (finish thickness, drainage slope, etc.).
3
Formwork Installation
Install beam formwork first, then slab formwork with safe shoring.
Formwork Installation
Install beam formwork first, then slab formwork with safe shoring.
3.1 Beam Formwork
- Install beam soffit (bottom) first, then sides.
- Ensure tight joints to prevent grout leakage.
- Provide strong bracing and correct beam dimensions.
3.2 Slab Formwork
- Install props/scaffolding, then main runners and secondary joists.
- Fix slab plywood; verify alignment and cleanliness.
- Apply release agent properly (not excessive).
Safety: Props must be on stable base + properly braced. No “loose” shoring allowed.
4
Rebar Installation (Beam → Slab)
Fix reinforcement in correct sequence with correct cover and anchorage.
Rebar Installation (Beam → Slab)
Fix reinforcement in correct sequence with correct cover and anchorage.
4.1 Beam Reinforcement
- Install bottom main bars.
- Install stirrups (spacing as drawing) with proper hooks.
- Install top bars (negative moment bars) and extra bars at supports.
- Provide lap splice or couplers per design.
4.2 Slab Reinforcement
- Fix slab bottom mesh/bars.
- Add top mesh/bars (if required) and extra bars over beams/supports.
- Reinforce around openings (edge trimming bars) as per drawing.
| Element | Typical Concrete Cover (site guidance) |
|---|---|
| Beam bottom & sides | 25–40 mm (confirm with drawing/spec) |
| Slab bottom | 20–25 mm (confirm with drawing/spec) |
| Roof slab top | 30–40 mm (confirm with drawing/spec) |
Important: Use chairs/spacers. Do not use broken bricks or stones as cover blocks.
5
Inspection Before Casting (Hold Point)
Engineer/QA approval required before any concrete pour.
Inspection Before Casting (Hold Point)
Engineer/QA approval required before any concrete pour.
5.1 Pre-Pour Checklist
- Formwork: alignment, dimensions, tight joints, stable bracing.
- Rebar: size, spacing, stirrup spacing, lap length/couplers.
- Concrete cover: spacers and chairs installed and correct.
- Openings/embeds: sleeves, conduits, anchor bolts in place.
- Cleanliness: remove debris, standing water, loose tie wire.
Site Rule: No pour without sign-off. Fix issues now, not after casting.
6
Concrete Casting (Beam + Slab)
Pour in the right order and compact properly to avoid honeycombing and cold joints.
Concrete Casting (Beam + Slab)
Pour in the right order and compact properly to avoid honeycombing and cold joints.
6.1 Pouring Sequence
- Start with beams (fill and vibrate).
- Continue to slab; keep pour continuous.
- Plan pour zones to avoid cold joints.
6.2 Compaction (Vibrator)
- Use mechanical vibrator with proper insertion spacing.
- Avoid over-vibration (segregation) and avoid hitting rebar/formwork aggressively.
- Vibrate beams carefully at congested zones (stirrups + bars).
6.3 Finishing
- Level slab to reference marks.
- Provide roof slope if required (drainage).
- Protect edges and openings immediately.
QC Point: Record slump, truck time, and cube/cylinder samples per project spec.
7
Curing
Start curing early to control cracking and gain strength.
Curing
Start curing early to control cracking and gain strength.
- Start curing within 12 hours (earlier if hot/windy).
- Methods: water curing, wet burlap, plastic sheet, curing compound (if approved).
- Minimum curing:
- Normal concrete: 7 days
- High importance / hot weather: 10–14 days
Hot Weather Tip: Cure more frequently to reduce shrinkage cracks.
8
Formwork Removal (Stripping)
Remove formwork only when concrete strength is adequate and approved.
Formwork Removal (Stripping)
Remove formwork only when concrete strength is adequate and approved.
| Element | Typical Minimum Time (Guidance) |
|---|---|
| Beam sides | 24–48 hours |
| Slab soffit (props remain) | 3–7 days |
| Beam soffit | 14–21 days |
Note: Actual stripping depends on concrete strength results + engineer approval.
9
Quality & Safety Control
Final checks, repairs, documentation, and safe site rules.
Quality & Safety Control
Final checks, repairs, documentation, and safe site rules.
9.1 Quality
- Inspect honeycombing and repair immediately (as per method statement).
- Check cracks, deflection, and slab level.
- Record cube/cylinder results; keep pour log.
9.2 Safety
- PPE mandatory (helmet, safety shoes, gloves, eye protection).
- Edge protection on slab perimeter and openings.
- No overload on fresh slab (material stacking control).
Site Habit: Daily toolbox talk during beam/slab works (risk: falling, collapse, electrical, vibration).
Quick Copy: Site Sequence
Drawings → Formwork → Beam Rebar → Slab Rebar → Inspection → Concrete → Curing
Optional add-ons: printable pre-pour checklist, photo slots for your project, and a daily QC log template.
Copied
Tags:
RC _ Site