SOP: Beam & Slab Construction (Site Execution)

Smart-Book SOP

SOP: Beam & Slab Construction (Site Execution)

A practical site workflow for GC teams: Formwork → Rebar → Inspection → Casting → Curing.

Purpose
Ensure safety, quality, and correct sequence for RC beam & slab works on site.
Scope
Formwork, rebar fixing, inspection, concrete casting, curing, stripping, QA & safety.
Responsible
Site Engineer • Foreman • Rebar Team • Formwork Team • Concrete Team • QA/QC • Structural Engineer (approval).
Easy Rule
Drawings → Formwork → Beam Rebar → Slab Rebar → Inspection → Concrete → Curing
1

Pre-Construction Preparation

Confirm drawings, materials, and site readiness before any formwork starts.

1.1 Drawing & Design Check

  • Review structural drawings: beam sizes, slab thickness, rebar details, bar marks.
  • Confirm span & support type (simply supported / continuous / cantilever).
  • Verify concrete grade & steel grade per spec.
  • Confirm standard/code used (ACI / BS / local project spec).

1.2 Material Check

  • Rebar diameter, grade, and delivery certificates (if required).
  • Formwork: plywood/steel panels, props, bracing, clamps.
  • Concrete supply: mix design, slump requirement, truck access.
  • Accessories: chairs, spacers, cover blocks, tie wire.
Site Tip: Prepare a “pour day plan” (truck route, pump location, vibrator quantity, manpower).
2

Setting Out & Level Control

Mark beam lines, slab boundaries, and control levels accurately.

  • Mark beam centerlines and slab edges from grid/architectural reference.
  • Check beam width & depth against drawings.
  • Set slab top level (reference: ±0.00) and check tolerance.
  • Confirm openings (stairs, ducts, sleeves) are located correctly.
QC Point: Fix any level error now—later it becomes expensive (finish thickness, drainage slope, etc.).
3

Formwork Installation

Install beam formwork first, then slab formwork with safe shoring.

3.1 Beam Formwork

  • Install beam soffit (bottom) first, then sides.
  • Ensure tight joints to prevent grout leakage.
  • Provide strong bracing and correct beam dimensions.

3.2 Slab Formwork

  • Install props/scaffolding, then main runners and secondary joists.
  • Fix slab plywood; verify alignment and cleanliness.
  • Apply release agent properly (not excessive).
Safety: Props must be on stable base + properly braced. No “loose” shoring allowed.
4

Rebar Installation (Beam → Slab)

Fix reinforcement in correct sequence with correct cover and anchorage.

4.1 Beam Reinforcement

  • Install bottom main bars.
  • Install stirrups (spacing as drawing) with proper hooks.
  • Install top bars (negative moment bars) and extra bars at supports.
  • Provide lap splice or couplers per design.

4.2 Slab Reinforcement

  • Fix slab bottom mesh/bars.
  • Add top mesh/bars (if required) and extra bars over beams/supports.
  • Reinforce around openings (edge trimming bars) as per drawing.
ElementTypical Concrete Cover (site guidance)
Beam bottom & sides25–40 mm (confirm with drawing/spec)
Slab bottom20–25 mm (confirm with drawing/spec)
Roof slab top30–40 mm (confirm with drawing/spec)
Important: Use chairs/spacers. Do not use broken bricks or stones as cover blocks.
5

Inspection Before Casting (Hold Point)

Engineer/QA approval required before any concrete pour.

5.1 Pre-Pour Checklist

  • Formwork: alignment, dimensions, tight joints, stable bracing.
  • Rebar: size, spacing, stirrup spacing, lap length/couplers.
  • Concrete cover: spacers and chairs installed and correct.
  • Openings/embeds: sleeves, conduits, anchor bolts in place.
  • Cleanliness: remove debris, standing water, loose tie wire.
Site Rule: No pour without sign-off. Fix issues now, not after casting.
6

Concrete Casting (Beam + Slab)

Pour in the right order and compact properly to avoid honeycombing and cold joints.

6.1 Pouring Sequence

  1. Start with beams (fill and vibrate).
  2. Continue to slab; keep pour continuous.
  3. Plan pour zones to avoid cold joints.

6.2 Compaction (Vibrator)

  • Use mechanical vibrator with proper insertion spacing.
  • Avoid over-vibration (segregation) and avoid hitting rebar/formwork aggressively.
  • Vibrate beams carefully at congested zones (stirrups + bars).

6.3 Finishing

  • Level slab to reference marks.
  • Provide roof slope if required (drainage).
  • Protect edges and openings immediately.
QC Point: Record slump, truck time, and cube/cylinder samples per project spec.
7

Curing

Start curing early to control cracking and gain strength.

  • Start curing within 12 hours (earlier if hot/windy).
  • Methods: water curing, wet burlap, plastic sheet, curing compound (if approved).
  • Minimum curing:
    • Normal concrete: 7 days
    • High importance / hot weather: 10–14 days
Hot Weather Tip: Cure more frequently to reduce shrinkage cracks.
8

Formwork Removal (Stripping)

Remove formwork only when concrete strength is adequate and approved.

ElementTypical Minimum Time (Guidance)
Beam sides24–48 hours
Slab soffit (props remain)3–7 days
Beam soffit14–21 days
Note: Actual stripping depends on concrete strength results + engineer approval.
9

Quality & Safety Control

Final checks, repairs, documentation, and safe site rules.

9.1 Quality

  • Inspect honeycombing and repair immediately (as per method statement).
  • Check cracks, deflection, and slab level.
  • Record cube/cylinder results; keep pour log.

9.2 Safety

  • PPE mandatory (helmet, safety shoes, gloves, eye protection).
  • Edge protection on slab perimeter and openings.
  • No overload on fresh slab (material stacking control).
Site Habit: Daily toolbox talk during beam/slab works (risk: falling, collapse, electrical, vibration).

Quick Copy: Site Sequence

Drawings → Formwork → Beam Rebar → Slab Rebar → Inspection → Concrete → Curing