Late Start (LS) & Late Finish (LF) in Microsoft Project

⏱️ Late Start (LS) & Late Finish (LF) in Microsoft Project

Late Start and Late Finish tell you the last safe moment a task can start/finish without delaying the project’s final finish date (CPM logic).

CPM (Critical Path Method) Schedule flexibility Float / Slack Construction-ready meaning

✅ What LS & LF mean (simple)

In Microsoft Project, Late Start (LS) and Late Finish (LF) answer this: “How late can this task move without pushing the project end date?”

Late Start (LS)
The latest date a task can start without delaying the project finish.
“How long can I wait before starting this task?”
Late Finish (LF)
The latest date a task can finish without delaying the project finish.
“How late can I finish this task safely?”
Important: If a task starts after LS or finishes after LF, you risk a project delay (finish date slips).

🖼️ Visual references

🔹 1) Late Start (LS)

Definition: The latest date a task can start without delaying the project finish.

If a task starts after its Late Start, the task is eating more than its allowed float and can push the project end date.

Memory idea: “How long can I wait before starting this task?”

🔹 2) Late Finish (LF)

Definition: The latest date a task can finish without delaying the project finish.

If a task finishes after its Late Finish, the project completion date can slip.

Memory idea: “How late can I finish this task safely?”

🧮 Relationship (easy formula)

Late Finish (LF) = Late Start (LS) + Task Duration Late Start (LS) = Late Finish (LF) − Task Duration
Tip: Think of LS/LF as the “backward plan” dates (calculated from the project finish date backward).

📊 Simple example

Task Duration Late Start Late Finish
Foundation 5 days Day 10 Day 15
👉 This means:
  • You can start as late as Day 10
  • You must finish by Day 15
  • Starting on Day 11 → ❌ risk of project delay

🟥 Critical Path connection (very important)

Critical tasks
  • Early Start = Late Start
  • Early Finish = Late Finish
  • Total Float = 0
Non-critical tasks
  • Late dates are later than early dates
  • Positive float (slack)
  • Can be moved safely (within float)
Site mindset: Critical tasks are “no delay allowed.” Non-critical tasks are “can move a bit” — but only up to LS/LF.

🔍 Why LS & LF matter (construction / engineering use)

  • 🛠 Reschedule safely without delaying handover
  • 👷 Move labor & resources to urgent tasks
  • ⚠️ Identify risky tasks with very small float
  • 📈 Recover delays using float wisely (crash/fast-track only when needed)
One-sentence memory trick:
Early = soonest possible
Late = last safe moment

📌 Next steps (tap to open)

Where do I show Late Start (LS) and Late Finish (LF) in Microsoft Project?

In a Task Sheet view, right-click any column header (like “Start” or “Finish”) → Insert Column → search for Late Start and Late Finish → insert them.

LS/LF vs Float vs Slack — what’s the difference?
  • LS/LF = last safe dates (schedule boundaries)
  • Total Float (Slack) = how much a task can slip without delaying the project finish
  • If Total Float = 0 → task is critical (no safe slip)
How do I use LS/LF to recover a delayed construction schedule?
  • Check tasks with small float (near-critical) and protect them.
  • Move resources from tasks with larger float to the urgent ones.
  • Use crashing (extra labor/overtime) only on tasks that affect the finish date.
  • Use fast-tracking carefully (overlap tasks) where quality risk is acceptable.
Want me to add a construction mini-case (foundation → columns → slab → walls → roof) and show exactly how LS/LF + float control manpower? Tell me your sample durations and I’ll build it.
Previous Post Next Post
📑