% Complete vs % Work Complete

% Complete vs % Work Complete in Microsoft Project

Good question — this is one of the most common points of confusion in Microsoft Project. Here’s the clear difference between % Complete and % Work Complete.

🧱 1. % Complete (Physical Progress)

Meaning:

  • Shows how much of the task’s duration (time) has been completed.
  • It’s time-based, not effort-based.
  • Tells you how far along the task is in terms of schedule.

Example:

  • A task has a 10-day duration.
  • After 5 days, you mark it as 50% complete — even if the actual work (effort) is not halfway done.

🟩 Formula

% Complete = (Actual Duration / Total Duration) × 100

So, if you’ve spent 3 days out of 6 planned → % Complete = 50%.

👷 2. % Work Complete (Effort Progress)

Meaning:

  • Shows how much of the total work (labor hours) has been done.
  • It’s effort-based, not time-based.
  • Measures how much work has been performed by resources.

Example:

  • A task has 100 hours of total work.
  • If 40 hours have been completed, % Work Complete = 40%, even if it’s only Day 2 of a 10-day duration.

🟩 Formula

% Work Complete = (Actual Work / Total Work) × 100

⚖️ In short comparison

Feature % Complete % Work Complete
Based on Duration (time) Work (effort/hours)
Focus Schedule progress Labor progress
Used by Project managers tracking time Resource managers tracking work
Example meaning “Half the scheduled time has passed.” “Half the work hours are done.”
Updates When you record progress by duration When you record progress by work hours

🧠 Tip from practice

  • Use % Work Complete to reflect actual site labor progress (real effort).
  • Use % Complete to reflect schedule progress for the client timeline.

For accurate project tracking, many engineers update both to show:

  • Physical progress (% Complete) = how much is built,
  • Effort progress (% Work Complete) = how much manpower has been spent.

🏗️ Example: House Foundation Work

Task Duration (Days) Total Work (Hours) Actual Duration (Days) Actual Work (Hours) % Complete % Work Complete
1. Excavation 4 32 4 32 100% 100%
2. Formwork 3 60 2 40 67% 67%
3. Reinforcement (Rebar) 4 80 4 60 100% 75%
4. Concrete Pouring 2 40 1 20 50% 50%
5. Curing & Finish 3 24 1.5 8 50% 33%

🔍 Let’s analyze

  1. Excavation — Finished on schedule and all work hours done → both 100%.
  2. Formwork — 2/3 days and 40/60 hrs → both 67%.
  3. Reinforcement — Time finished (4/4 = 100%) but work 60/80 (75%) → risk of delay.
  4. Concrete Pouring — Halfway in both schedule and effort → 50% / 50%.
  5. Curing & Finish — Half the duration (50%) but only 33% work → labor slower than planned.

🧭 Summary in Plain Words

Situation What it Tells You
% Complete > % Work Complete Work is slower than planned → may need more labor or time.
% Work Complete > % Complete Work is progressing faster than schedule → good productivity.
Both equal Progress matches the plan perfectly.

💡 In Microsoft Project

  • Update both in Task Information → General / Tracking tabs.
  • Show both columns in the Gantt Chart view to monitor schedule vs. work progress clearly.

Would you like me to show this same table as a Microsoft Project–style Gantt (with progress bars for both % values)? See the demo below.

Interactive Demo — % Complete vs % Work Complete

Top bar = % Complete (schedule). Bottom bar = % Work Complete (effort).

% Complete % Work Complete
# Task Dur (d) Work (h) Act. Dur (d) Act. Work (h) Gantt

Dual Progress Gantt — % Complete vs % Work Complete

Top bar = % Complete (schedule). Bottom bar = % Work Complete (effort).

% Complete (Time / Schedule) % Work Complete (Effort / Labor)
WBS Task Duration (d) Work (hrs) Actual Dur. (d) Actual Work (hrs) % Complete % Work Complete Gantt
Previous Post Next Post
📑