How to Create a Bill of Quantities (BOQ) and Material Requisition Plan

Go to main contence: Standardized Procedures and Workflows for Construction Team

A Bill of Quantities (BOQ) and a Material Requisition Plan are essential tools in construction planning. They help you estimate costs, plan procurement, and control resources effectively.

🔹 1. What is a BOQ?

A BOQ is a detailed document that lists the quantities of materials, labor, and other work items required to complete a project. It helps:

  • Estimate total project cost
  • Get fair and comparable bids from contractors
  • Plan for procurement and budgeting

🔹 2. Steps to Create a Bill of Quantities (BOQ)

a. Study Project Drawings & Specs

  • Review architectural, structural, and MEP drawings.
  • Read project specifications for material standards and methods.

b. Break Down the Project into Work Items

Use the Work Breakdown Structure (WBS) to divide the project into sections:

  • Site work
  • Foundation
  • Superstructure
  • Roofing
  • Finishes

c. Measure Quantities

  • Volume (m³) – for concrete, excavation
  • Area (m²) – for flooring, plaster
  • Length (m) – for rebar, wiring
  • Number (pcs) – for fixtures, doors

d. Use a Standard Format

Organize the BOQ in a table like this:

Item No Description of Work Unit Quantity Unit Rate Total Cost
1 Excavation 100 $10 $1,000
2 Concrete (Footing) 50 $80 $4,000
3 Reinforcement (Rebar) kg 500 $1.20 $600

🔹 3. What is a Material Requisition Plan?

A Material Requisition Plan is a document that outlines the materials needed for each phase of the project, with delivery timelines. It helps ensure materials are available when needed, avoiding delays.

🔹 4. Steps to Create a Material Requisition Plan

a. Use the BOQ as a Reference

  • Identify all materials listed in the BOQ.

b. Match Materials to Project Schedule

  • Link material needs to construction phases (e.g., cement needed during foundation phase).

c. Create the Material Schedule Table

Material Quantity Required Date Delivery Lead Time Supplier Status
Cement 300 bags June 10 3 days ABC Co. Pending
Rebar 2 tons June 12 5 days XYZ Ltd. Ordered

🔹 5. Tips for Accuracy

  • Use digital tools (like Excel, PlanSwift, or Bluebeam) for take-offs and tracking.
  • Double-check quantities with engineers.
  • Coordinate with the procurement and site teams.

✅ Benefits

  • Helps control project cost
  • Ensures timely procurement
  • Improves planning and reduces material waste
  • Increases contractor transparency